27-Aug-2010
 

Monitoring pfase I, cancelled phase II
Due to the first evaluation and monitoring results of phase I we have decided to help with further establishment of the water committees and organise...

12-May-2010
 

Upscaling in 2010
The upscaling phase, Bohol 2, has been presented as a case study during the Women for Water Regional Working Conference in Sri Lanka November 2009....

12-May-2010
 

Results in 2009
The first part of the project has been implemented with main results: One reservoir of 28.500 litre (for 55 households) in Caharan. 45...

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
Carahan: Enjoying clean and healthy drinking water

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
Carahan: Chairperson at water point

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
Carahan: Water tank completed

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
Carahan: connection of pipes from water tank

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
Lantay: Ecosan subsurface collection of urine

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
Lantay: Construction of handwashing facility and urinoir

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
Lantay: Picture update construction of ecosan toilet

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
Lantay Picture update: Kids enjoying clean and safe drinking water.

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
Lantay: Picture update completion of roof of watertank

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
Lungon: Picture of completed watertank

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
Lungon: Picture update on watertank construction

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
Lungon: Picture update on watertank construction

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
Lungon: Picture update watertank construction

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
Lungon: Picture update of water tank construction works.

16-Jun-2009

Water & Sanitation for Bohol, The Philippines
The implementation of the Pansul project has started.

09-Mar-2009

Water & Sanitation for Bohol, The Philippines
This is a Picture update of the construction works of the project at Lantay.

Complete

Funding

Raised: € 50,574

Fully funded

See funding details ►

Tools for this page

Embed a live link to this project to your web site or blog.



Sign in to add update
Permalink to this project
Subscribe to the RSS feed of this project

Project partners

Agriterra
Arnhem, Netherlands


Aqua for All
Den Haag, Netherlands


WfWP
The Hague, Netherlands


WOPD
Bohol, Philippines


ZijActief
Alphen aan den Rijn, Netherlands


Akvo Ref: 60