Borehole Rehabilitation

RSS

Borehole rehabilitation in Garalol, Mauritania

◀ Back to main project page

Funding details

Request posted 11-Jun-2009

1,243
views

Project Budget

Employment costs: € 900
Building Material costs: € 14,898
Other costs: € 1,787
Total: € 17,585

Individual donations

Individual raised*: € 54
Anonymous: € 54

* The amount indicated is the donation minus transaction fees.


Current funders

WvW 2009
Den Haag, Zuid-Holland, Netherlands

Grant: € 2,550

Aqua for All
Den Haag, Zuid-Holland, Netherlands

Grant: € 8,766

Silent Work
Edam, Noord-Holland, Netherlands

Grant: € 6,216

Complete

Funding

Raised: € 17,585

Fully funded

Latest updates

17-Feb-2010

Project finished! Fresh water for Garalol
The project is finished. The 3000 villagers of...

17-Feb-2010

Renovation of tower
Also the engineers cabin is renovated and a fence...

17-Feb-2010

Tools for this page

Embed a live link to this project to your web site or blog.



Sign in to add update
Permalink to this project
Subscribe to the RSS feed of this project

Project partners

Aqua for All
Den Haag, Netherlands


Silent Work
Edam, Netherlands


Wandelen voor Water
Den Haag, Netherlands


WvW 2009
Den Haag, Netherlands

Comments

Add comment ►

De onderstaande school heeft gelopen voor het project van de Stichting Silent Work in Mauritania: 1. OBS De Langereisschool Address: Noorddijkerweg 52, 1645 VG Ursem Web: http://bit.ly/czmjLA Hartelijk dank voor jullie inzet!
Luuk Diphoorn, 2010-05-10 11:23

On the 27th of September 2009 Martin Vliet celebrated his birthday. He used this opportunity to raise funds for this project. In total he managed to raise €700, which in turn has been dubbeld by Aqua for All. Martin: Thank you so much for your efforts, I’m sure the people in Mauritania are very grateful!
Luuk Diphoorn, 2009-10-15 11:08