Borehole Rehabilitation
Borehole rehabilitation in Garalol, Mauritania
Status
Complete
Focus area
Location
Garalol
Brakna, Mauritania
The existing water well is not deep enough and will be drilled deeper. In addition, the water tank and pump will be repaired.
Target benchmarks
- 1 functioning water systems
- 3000 persons with access to improved water for 30 years
The main goal is to provide the people of Garalol with safe drinking water. The rehabilitated borehole will provide sufficient water of good quality, for the whole village, for the next 30 years.
The long term goal is to reduce child mortality and improve the overall health of the villagers
Target benchmarks
- 1 functioning water systems
- 3000 persons with access to improved water for 30 years
Sustainability of the project is guaranteed by emphasising capacity building of the local people. They have ownership over the project and put in a lot of work and financial contribution.
To be able to maintain the water well properly, an estimation of exploitation costs has been made. The villagers will have to pay a little for the water they take from the well, where the tariff is different for villagers with less financial resources. The collected money will be used for the operation and maintenance of the water system.
Related to this project
Comments
You must be signed in to add a comment
Luuk Diphoorn
2009-10-15 11:08
On the 27th of September 2009 Martin Vliet celebrated his birthday. He used this opportunity to raise funds for this project. In total he managed to raise €700, which in turn has been dubbeld by Aqua for All. Martin: Thank you so much for your efforts, I’m sure the people in Mauritania are very grateful!
The comments are owned by whoever posted them. We are not responsible for them in any way.
Project updates
Project finished! Fresh water for Garalol
2010-02-17 00:42 by Victor Hanenburg, Silent Work, via web
Access to fresh water - Garalol
The project is finished. The 3000 villagers of Garalol have access to fresh drinking water. There is enough water for at least 30 years. The health situation of the people will quickly improve and especially the child mortality rate is expected to decrease significantly.
Renovation of tower
2010-02-17 00:33 by Victor Hanenburg, Silent Work, via web
Fenced water tower - Garalol
Also the engineers cabin is renovated and a fence is placed around the watertower to protect the tower against damaging hurds of animals.
Singing and dancing around the new fountain
2010-02-17 00:28 by Victor Hanenburg, Silent Work, via web
The updates are owned by whoever posted them. We are not responsible for them in any way.
Funding
Raised: € 17,585
This project is
Fully funded
2009-06-11 Request posted
Current funders

Nieuwegein, The Netherlands
Grant: € 2,550

Nieuwegein, The Netherlands
Grant: € 8,766

Edam, The Netherlands
Grant: € 6,216
Donations from individuals
![]()
Total: € 54
Page tools
Partners
Field partner

Edam, The Netherlands
Support partner

Nieuwegein, The Netherlands
Sponsor partner

Wandelen voor Water
Nieuwegein, The Netherlands